Automotive supply chain risk software scorecard

Give each provider the same critical part, supplier records, and disruption scenario. Ask the provider to show which parts and plants could be affected, how much time you have to act, and what evidence supports each result.

Worked example for a port delay

In this modeled example, an inbound wiring harness may arrive too late for an assembly plant. The team needs at least four hours to verify stock and decide whether to resequence production.

Mark a check Pass when the evidence meets the requirement, Review when a gap needs follow-up, or Missing when you have no evidence. Set your minimum warning time before you compare providers.

  1. Critical part coverage

    Map a critical part from its Tier-2 site through Tier 1 to the receiving plant.

    Review. The map links the harness to the assembly plant. The Tier-2 site still needs confirmation.

  2. Supplier link evidence

    Show the source and check time for each link. Label each link confirmed, inferred, or unknown.

    Pass. The supplier declaration confirms the Tier-1 link. The tool marks the Tier-2 link as inferred.

  3. Time to act

    Compare the alert time with the earliest impact time. Check whether the team can act in that window.

    Pass. The alert arrives at 08:20. The earliest modeled impact is 14:00. The team has 5 hours and 40 minutes.

  4. Response options

    Show an owner, a deadline, and the required approval for each response.

    Review. The buyer can check a partial delivery. The brief gives no owner for approval of extra freight cost.

  5. Decision record

    Export the alert, evidence, owner, and decision. Check that the record shows later changes.

    Missing. The team has no export to check in this exercise.

Assign an owner and a next action to each open check. In this example, ask the supplier to confirm the Tier-2 site and ask the provider to show the decision export before you approve a pilot.